PROJECT MANAGEMENT

ERC offers project management services based on experience gain from Equinor’s MODU new built program with delivery of more than 17 complex MODU newbuilt industry projects.

Project management.png

EPCIC execution characteristics:

  • NCS Authority-, Flag- and DNV Class requirements + Company activity requirements

  • Mature FEED & TBS - Proven design concept and applied technologies

  • Approved Engineering alliance, aligned MEL and unique Aker BP requirements.

  • Yard is FEED/Design responsible.

  • Yard is responsible for all MC & Completion activities

  • Defined Accept criteria

  • Defined commissioning program

  • Defined TQ/VO/Punch management system

  • Late delivery payment incentives


Framing EPCIC execution strategy

Company’s main responsibilities:

  • Defining Design Basis

  • Prequalify Yards

  • Approve FEED design at DG3

  • Defined EPCIC Turn-Key delivery requirements at DG3

  • Defined Company’s Accept Criteria’s

  • Define Company’s Acceptance Test Program

  • EPCIC contract following up strategy

The Contractor/yard’s responsibility:

  • Full responsibility and control, incl interface management of CPI

  • Control interface management

  • Ensure constructability friendly FEED design.

  • QA control of handover from FEED to Detail engineering.

  • Change management procedures


EPCIC Contract strategy

Yard contract

  • Technical Building Specification.

  • Yard is FEED/Design responsible.

  • Yard is responsible for all MC & Completion activities

  • Defined Accept criteria’s

  • Defined commissioning program

  • Defined TQ/VO/Punch management system

  • High tail end delivery payment schedule

  • High liquidated damage

  • Company takes ownership at time of delivery from yard

  • Company payment is guaranteed with performance bond

  • Bank guaranty of contract price through 2 years warranty


EPCIC risk  mitigation strategy

DG1-DG2

  • Prequalify yards and operational management companies.

  • Define prequalified FEED/Detail engineering companies

  • Prequalify main equipment subcontractors (MEL)

  • Approved Engineering alliance, MEL and TORG requirements.

DG2-DG3

  • Ownership of SOW (FEED&TBS)

  • EPCIC turn-key delivery responsibility

  • Commissioning management system

  • Document Control, LCI and Maintenance Management system

  • Authority-, Flag- and DNVGL Class requirements and notations

  • Mature FEED & TBS

DG2-DG3

  • EPCIC project following up strategy

DG4-Operation

  • Asset operational management strategy


Mobilization / Rig intake

  • Rig intake Project Service reports

    • Phase 1, pre-hire check

    • Phase 2, full condition survey

    • Phase 3, full acceptance test

  • Rig intake reports:

    • ­Rig performance benchmarking reports

    • ­Well performance benchmarking reports

    • ­Contract Strategy

    • ­Rig Inspection, Verifications and Acceptance reports

  • Commissioning procedures

    • ­Acceptance Test Procedures.

    • ­System Integration Test Procedures


QUALITY & RISK MANAGEMENT

Providing senior QRM/HSE service, managing project and operational risk activities.