PROJECT MANAGEMENT
ERC offers project management services based on experience gain from Equinor’s MODU new built program with delivery of more than 17 complex MODU newbuilt industry projects.
EPCIC execution characteristics:
NCS Authority-, Flag- and DNV Class requirements + Company activity requirements
Mature FEED & TBS - Proven design concept and applied technologies
Approved Engineering alliance, aligned MEL and unique Aker BP requirements.
Yard is FEED/Design responsible.
Yard is responsible for all MC & Completion activities
Defined Accept criteria
Defined commissioning program
Defined TQ/VO/Punch management system
Late delivery payment incentives
Framing EPCIC execution strategy
Company’s main responsibilities:
Defining Design Basis
Prequalify Yards
Approve FEED design at DG3
Defined EPCIC Turn-Key delivery requirements at DG3
Defined Company’s Accept Criteria’s
Define Company’s Acceptance Test Program
EPCIC contract following up strategy
The Contractor/yard’s responsibility:
Full responsibility and control, incl interface management of CPI
Control interface management
Ensure constructability friendly FEED design.
QA control of handover from FEED to Detail engineering.
Change management procedures
EPCIC Contract strategy
Yard contract
Technical Building Specification.
Yard is FEED/Design responsible.
Yard is responsible for all MC & Completion activities
Defined Accept criteria’s
Defined commissioning program
Defined TQ/VO/Punch management system
High tail end delivery payment schedule
High liquidated damage
Company takes ownership at time of delivery from yard
Company payment is guaranteed with performance bond
Bank guaranty of contract price through 2 years warranty
EPCIC risk mitigation strategy
DG1-DG2
Prequalify yards and operational management companies.
Define prequalified FEED/Detail engineering companies
Prequalify main equipment subcontractors (MEL)
Approved Engineering alliance, MEL and TORG requirements.
DG2-DG3
Ownership of SOW (FEED&TBS)
EPCIC turn-key delivery responsibility
Commissioning management system
Document Control, LCI and Maintenance Management system
Authority-, Flag- and DNVGL Class requirements and notations
Mature FEED & TBS
DG2-DG3
EPCIC project following up strategy
DG4-Operation
Asset operational management strategy
Mobilization / Rig intake
Rig intake Project Service reports
Phase 1, pre-hire check
Phase 2, full condition survey
Phase 3, full acceptance test
Rig intake reports:
Rig performance benchmarking reports
Well performance benchmarking reports
Contract Strategy
Rig Inspection, Verifications and Acceptance reports
Commissioning procedures
Acceptance Test Procedures.
System Integration Test Procedures
QUALITY & RISK MANAGEMENT
Providing senior QRM/HSE service, managing project and operational risk activities.